Service disruptions on March 9, 10, 17, and 20 in different parts of Davao City
MARCH 20, 2024 UPDATE
--------------------------
Davao Light and Power Co., Inc. will conduct a series of power interruptions on March 9, 10, 17, and 20, 2024, affecting customers in different parts of Davao City.
A switching power interruption will be conducted on March 9, Saturday, for 2 hours and 30 minutes from 4:00 a.m. to 6:30 a.m. to facilitate the normalization of ERA Substation. Specifically affected are customers from Abreeza to Carmelite Bajada, Buhangin Road up to Samulco, and all neighboring areas.
A separate switching power interruption will be conducted for 1 hour anytime between 12:00 a.m. to 2:00 a.m. on March 10, Sunday, to facilitate the transfer of loads to nearby substations. Meanwhile, the normalization or return of loads to their normal set-up will be for another 1 hour anytime between 12:00 a.m. to 2:00 a.m. on March 20, Wednesday. These disruptions are necessary to conduct upgrading works at the 138kV line of ERA Substation.